APPLICABILITY: Applicable to co-generation facilities which meet ALL of the following conditions:
1. Generator must be installed at a service receiving electric service under Schedule No. 21, 22, 24, 25, 28, 31, 32, or 33 (Primary Service).
2. Generator must be incidental to the Primary Service, installed on the customer’s premises, and used to supply some or all of the customer’s loads.
3. Generator must be less than 25 KVA and must be less than 80% of the installed transformer capacity of the Primary Service.
4. Generator must have a maximum output of less than 10% of the nearest source side primary voltage protective device.
5. Generator must have the same output voltage and phasing as the Primary Service.
6. Generator must be a fuel cell or other renewable energy powered generator controlled by an inverter which has been designed, tested, and UL certified to UL1741 and IEEE929 standards.
7. Generator must have positive “anti islanding” capability per UL1741.
8. Generator must have output voltage with less than 1% Total Harmonic Distortion (THD), current output with less than 2% THD, and be operated with a 1.0 to .95% lagging Power Factor. Leading power factor operation will not be permitted.
9. Generator must be provided with a “Visible Disconnect Switch” per NESC requirements which can be padlocked in the OPEN position and is accessible to Garkane personnel at all times. Disconnect must be permanently and visibly marked as “GENERATOR DISCONNECT” in letter at least 2” high.
METERED ENERGY: Energy metered under this rate shall be the net energy returned to the distribution system during any billing period.
MONTHLY BILL:
Base Rate $12.50
Energy Credit $0.015
MINIMUM: The minimum monthly charge shall be the Base Rate, and any increase required under the Line Extension Policy. Payment of the Base Rate does not entitle the consumer the use of any kWh of electricity.
TEMPORARY DISCONTINUANCE OF SERVICE: If a consumer requests reconnection of service at the same location, he shall be required to pay the Base Rate for each of the intervening months. Non-use of service for 12 months shall make the premises subject to removal under the Idle Service Regulation.
ELECTRIC SERVICE REGULATIONS: Service under this schedule will be in accordance with the above conditions and the Electric Service Agreement between the customer and the Association. The Electric Service Regulations of the Association on file with and approved by the Public Service Commission of Utah, including future applicable amendments, will be considered as forming a part of and incorporated in said Agreement.
TERMS OF PAYMENT: Credits due under this account will be credited to the Primary Service Account. Unused credits expire at the end of each calendar year.
EFFECTIVE: May 1, 2002