Small Generator Interconnection Application
Small Generator Interconnection Application
An Interconnection Request is considered complete when it provides all applicable and correct
information required below.
Preamble and Instructions
An Interconnection Customer who requests a Qualified Facility interconnection must submit this
Interconnection Request by hand delivery, mail, e-mail, or fax to the Cooperative.
Processing Fee or Deposit:
If the Interconnection Request is submitted to be evaluated under a Fast Track Process, the nonrefundable
processing fee is $250.
If the Interconnection Request is submitted under the Study Process, whether a new submission or an
Interconnection Request that did not pass the Fast Track Process, the Interconnection Customer shall
submit to the Cooperative a deposit of $1,000.
APPLICATION: Click to download