Small Generator Interconnection Application

An Interconnection Request is considered complete when it provides all applicable and correct

information required below.

 

Preamble and Instructions

An Interconnection Customer who requests a Qualified Facility interconnection must submit this

Interconnection Request by hand delivery, mail, e-mail, or fax to the Cooperative.

 

Processing Fee or Deposit:

If the Interconnection Request is submitted to be evaluated under a Fast Track Process, the nonrefundable

processing fee is $250.

 

If the Interconnection Request is submitted under the Study Process, whether a new submission or an

Interconnection Request that did not pass the Fast Track Process, the Interconnection Customer shall

submit to the Cooperative a deposit of $1,000.

 

APPLICATION: Click to download

 

 